Greater Jakarta LRT Project Phase I Progress Reaches 77.3%
星期四, 1 十月 2020

As of 25 September 2020, PT Adhi Karya (Persero) Tbk. (ADHI) reported that the progress of Greater Jakarta LRT Project Phase I has reached 77.3%, including the service line 1 Cawang-Cibubur at 91.2%, service line 2 Cawang-Kuningan-Dukuh Atas at 73% and service line 3 Cawang-East Bekasi at 70.7%. ADHI has also received the sixth funding installment of this project worth Rp1.8 trillion from the government via PT Kereta Api Indonesia (Persero).