The Head of the Toll Road Management Agency (BPJT) Wilan Oktavian reported that the construction of Yogyakarta-Bawen Toll Road, which spans the total length of 75.12 km, is accelerated. From the total of six sections, Section 1 of Sleman-Banyurejo which spans the total length of 8.80 km, and Section 6 of Ambarawa-Bawen which spans 5.21 km are under construction. The Section 1 progress has reached 77.68% and is planned to be completed in the second quarter of 2026 and Section 6 has reached 61.90%, while the remaining sections are under land acquisition process.