Although the construction of 14.95-kilometer Harjamukti (Cibubur)-Cawang lane of LRT Jabodebek has been completed, facilities for signal, telecommunication and electricity haven’t been available. Furthermore, the construction of the station has only progressed by 50%. Other facilities such as road a...