Kataraja Toll Road 1 Reaches 94.9%, PTPP Completes Load Testing

星期二, 8 九月 2026

PT PP (Persero) Tbk (PTPP) is pushing to complete Section 1 of the Kamal-Teluk Naga-Rajeg (Kataraja) Toll Road, which has reached 94.9% progress, with a contract value of Rp1.46 trillion before VAT and completion targeted for October 14, 2026. The toll road will improve Jakarta-Banten connectivity, including access to Soekarno-Hatta Airport and PIK 2, while supporting logistics distribution and industrial and warehousing development in northern Tangerang.