Government Aims to Complete Pattimura Toll Access in 2027

星期六, 16 五月 2026

The Ministry of Public Works (PU) confirmed that the construction of the Pattimura Toll Access on the Semarang–Solo Toll Road segment will be completed in 2027. The project is a part of the Semarang-Solo Toll Road network constructed by the Toll Road Business Agency (BUJT) PT Trans Marga Jateng since April 2026 with the construction value of Rp113.35 billion. The project which spans the total length of 1.66 kilometers required the total land area of 18,731 square meters of which 97.33% has been acquired.